tug-of-warIn a remarkably tangled construction dispute, the property owner interpleaded roughly $260,000, after a dispute arose between the general contractor and a sub.  One of the interpleaded parties argued that the owner “faces only separate obligations,” augmented by the fact that the Mississippi statute relied upon the subcontractor to freeze the funds was declared unconstitutional. Auto Parts Manufacturing Mississippi, Inc. v. King Construction of Houston, No. 14-60217 (May 8, 2015).  The Fifth Circuit disagreed: “The first stage of interpleader only is concerned with whether multiple claims have been asserted, or may be asserted, against a disinterested stakeholder, not whether those claims have merit.” The Court reminded that “interpleader jurisdiction is determined at the time the interpleader complaint is filed . . . ‘and subsequent events do not divest the court of jurisdiction once properly acquired.'”